HDPE pipe selected for the project is manufactured by KWH Pipe using DOW™ DGDB- 2480 NT HDPE resin. |
Weholite has been used in many municipal and industrial applications including new pipeline and pipeline rehabilitation projects and offers substantial savings in weight for increased ease of installation and cost effectiveness. This was a key factor in KAP’s decision to include approximately 3,100 feet of 132 inch inside diameter Weholite pipe in two parallel lines, according to Paul Mongelli, Site Engineer with Kiewit at the Wawaitin Generating Station Project.
“This is our first design/build project with OPG,” said Mongelli. “We did our homework and decided against using concrete due to several construction and operational benefits of HDPE. The Weholite pipe can be installed in less man hours with less equipment so there was a significant cost savings during construction. It also offers OPG some nice benefits once the plant is up and running.”
“The ability to extrusion weld joints is a tremendous benefit of HDPE pipe,” Mongelli said. “We can typically weld one to two joints per day resulting in a much improved timeline for this part of the project. And, there’s no building forms, pouring concrete or drying time. The ability to extrusion weld the joints greatly reduced the time and manpower needed for the project.”
According to the Plastic Pipe Institute, HDPE’s heat-fused or extrusion welded joints create a leak free, self restraint, monolithic pipe structure; the welded joint will also eliminate infiltration into the pipe and exfiltration into the environment. Maintenance benefits also made HDPE a solid fit for the Wawaitin Generation Station.
“We anticipate zero maintenance costs with the HDPE pipe,” said Bruce McIvor, Site Representative with OPG.
In addition to the facility coming to the end of its service life, OPG is replacing the generating station because of an 18% energy loss with the system due to the 300 km of transmission lines the power must travel to get to the grid.
“The new system will change the generating station from 25 to 60 Hz allowing connection directly to the local distribution system eliminating the need to transmit the energy from Timmins to Sudbury. This change will eliminate significant energy losses and free up a transmission corridor,” McIvor said.
“By refurbishing, upgrading and expanding our hydroelectric capacity across the province, we are diminishing our reliance on burning coal for fuel and plan to stop burning coal altogether by the end of 2014. OPG is committed to reducing our carbon footprint through projects like this one and enjoy the opportunity to work with companies like KWH and Dow which have similar corporate goals,” McIvor said.
More Industrial WaterWorld Articles
Past IWW Issues