The Arzew desalination plant will produce an estimated 80,000 m3/day. Image provided by BVA.
Click here to enlarge imageA technology feasibility study undertaken by Black & Veatch Africa in 1999 concluded that the preferred plant process would be a multistage flash (MSF) distiller with feed steam derived from simple cycle gas turbines and heat recovery steam generators.
BVA and AEC confirmed the Japanese consortium of Itochu Corporation and IHI (Ishikawajima-Harima Heavy Industries) as the preferred bidder in an EPC (Engineering-Procurement-Construction) bidder evaluation and selection process undertaken between November 2001 and January 2002.
This evaluation process was the first carried out since the formation of both AEC and Kahrama and it was important that it was seen to be impartial. In the technical evaluation, a ranking of bid compliance was realised in parallel with adjustments to a customised financial model for each bidder to reflect differences in availability, performance, operation and maintenance costs, spares, payment terms and other factors. The president and director general of AEC presided over the commercial opening, attended by the Minister of Energy & Mines, other interested parties and the news media. The respective financial models were projected onto a large screen, visible to all, as the contents of the commercial bids were inserted into the model. The preferred bidder, that with the highest overall net present value for the project, was declared immediately during the commercial bid opening.
The optimum configuration of the plant is based on three General Electric PG9171 (9E) gas turbines using evaporative coolers, each with an associated heat recovery steam generator (HRSG). The output steam (618,000 kg/hr) is distributed to each of three MSF unit brine heaters in a common header for flexibility during maintenance and outages. The MSF performance ratio is 6.25. The plant will be brought into commercial operation in three phases, each phase corresponding to a power/desalination train, in two-month intervals.
Seawater will be extracted from the Port El Djedid deep-water harbour at Arzew at the rate of approximately 40,000 kg/hr and at an average temperature of 24oC. The plant discharges to the external side of the harbour breakwater to avoid recirculation and is expected to experience a 10oC temperature rise in the process.
Natural gas will fuel the plant. Power from the site will be connected by Sonelgaz at 220 kV to their existing grid via approximately seven km of new overhead line.
All parties are confident that the project is on track to commercially produce both power and water before the end of 2004.