Finning expands green electricity generation for Thames Long Reach

July 17, 2007
Finning Power Systems is increasing the amount of green electricity produced by Thames Long Reach sewage plant from 2.3MW to 3.3MW with the installation of a third CHP biogas generator. Phase two of the turnkey installation is due for completion later this year. The project involves installing and commissioning a customized Cat G3516 biogas generator set as a combined heat and power system, expanding the switchgear with an additional HV board cabled to the existing system and expanding...

BERKSHIRE, UK, July 16, 2007 -- Finning Power Systems is increasing the amount of green electricity produced by Thames Long Reach sewage plant from 2.3MW to 3.3MW with the installation of a third CHP biogas generator. Phase two of the turnkey installation is due for completion later this year.

The project involves installing and commissioning a customized Cat G3516 biogas generator set as a combined heat and power system, expanding the switchgear with an additional HV board cabled to the existing system and expanding the LIMA remote control and monitoring system. Finning will also complete any necessary civils work such as building, sound attenuation and additional pipework.

Phase 1 of the turnkey project, to produce electricity from the methane gas produced by the sewage, was also completed by Finning Power Systems.

Now, due to the more efficient generation of methane gas, Thames Water has decided to add a third CHP biogas generator set. Original projections were for 17,000m3 of methane gas. This has since increased to 22,000 m3 and improving the sewage digestion system will further increase the methane available for power generation to 28,000 m3.

The extra electricity produced by the third biogas generator will be used to power the expanded sewage operation and to also export more green power to the national grid. The extra 1MW provides enough electrical power for 200 homes a day.

The aggressive nature of sewage gas means that Finning Power Systems fully hardened the Cat generator set before it was installed. This involved using special lubricants with high temperature cooling jackets.

The current installation provides enough electrical output to power the 1.8MW sewage works load making the plant completely carbon neutral. In addition, the power station can export electricity to the grid depending on the tariff available at the time.

A back up diesel generator set provides failsafe power generation if both of the existing biogas generator sets fail and another auxiliary diesel generator provides a third level of back up.

The LIMA control system can switch between generator sets automatically and also prioritize which circuits are powered if there is a problem. Again two levels of redundancy means that generator sets can be switched automatically or manually using LIMA, or manually using key switches. It also allows remote monitoring of the whole system as part of Finning's 24/7 maintenance contract.

In addition the methane gas can be stored in double skinned expandable balloon holders so the amount of fuel used, and therefore electrical power generated, can be managed.

The CHP system also generates 2MW of heat. This heats up the sewage digestors to generate more methane gas for power generation.

Comments Thames project manager, David Watts: "When the original power station burnt down in 2000 we decided that it was more energy efficient and environmentally friendly to use the methane gas to generate electricity rather than burn it off.

"We originally chose Finning for the project because they can supply the complete turnkey solution, not only supplying the customized Cat generator, but also the design, installation and commissioning and full service back up. Phase two of the project will further increase our capacity to generate green electricity."

###

Sponsored Recommendations

NFPA 70B a Step-by-Step Guide to Compliance

NFPA 70B: A Step-by-Step Guide to Compliance

How digital twins drive more environmentally conscious medium- and low-voltage equipment design

Medium- and low voltage equipment specifiers can adopt digital twin technology to adopt a circular economy approach for sustainable, low-carbon equipment design.

MV equipment sustainability depends on environmentally conscious design values

Medium- and low voltage equipment manufacturers can prepare for environmental regulations now by using innovative MV switchgear design that eliminates SF6 use.

Social Distancing from your electrical equipment?

Using digital tools and apps for nearby monitoring and control increases safety and reduces arc flash hazards since electrical equipment can be operated from a safer distance....